Tweet/Garot has been a family-owned mechanical contracting business for over 120 years. Beyond simply designing and building high-quality mechanical solutions, our industry-best workforce provides a complete commitment to each project and extraordinary customer service.
Tweet/Garot design teams continue to push limits of technology within the construction industry. We have created the ability to provide a more detailed mechanical concept model to our construction partners with less information, and in record times.
With nearly 155,000 square feet of prefabrication space, our customers are confident in our ability to not only reduce our man-hours on site and reduce transportation costs, but also help shorten the time required to complete our critical, preliminary work.
Tweet/Garot is dedicated to providing our clients with a smarter, energy-efficient, and more comfortable facility, always functioning at peak performance.
Tweet/Garot specializes in—and is recognized for—our ability to work around our customers’ demanding schedules, no matter what market. We utilize fast-track construction methodology, virtual design technology, and continuous improvement in all that we do. Our clients know that Tweet/Garot thrives on solving challenges.
In 2009, planning started for a $45 million dollar project in Antigo for the replacement of Langlade Hospital. The design includes the construction of a two-story, 25 patient bed facility of 90,000 square feet. This new facility is replacing an aged building that was constructed in 1933. Tweet/Garot Mechanical was contracted to fabricate and install all of the HVAC and Plumbing systems.
The HVAC systems include high-efficiency boilers, a high-efficiency heat recovery chiller, and in-floor heating in the lobby. Saving one million dollars in energy costs over a five-year period is becoming a reality for the new Langlade Hospital. The energy-saving measures include:
Pre-fabrication of plumbing components, piping spools, duct, VAV assemblies, and radiant heating components were all done in Tweet/Garot’s Green Bay shop and shipped to the site for quick and easy installation. Every pre-fabricated item was marked with the floor, and room location. Movable racks were built to wheel the items off the delivery truck and into the building to the tagged locations.
The plumbing system consists of hot water heaters and holding tanks, mixing valves, all bathroom fixtures, and stainless steel kitchen fixtures. We installed the underground plumbing as well as fresh water and waste piping. In addition, Tweet/Garot provided the installation of the medical gas system.
Tweet/Garot performed all the coordination and BIM drawings for all trades. Collision detection was identified up-front so that re-work was eliminated during the installation phase.