Tweet/Garot was brought on board to partner for the successful completion of the $165 million paper machine rebuild project, working on the installation of heavy industrial ventilation.

The tight timeline and work occurring several states from Wisconsin presented many challenges. The sheer size and scope of the project present itself with a 34 day long, 24 hours per day shutdown. Some of the challenges to this project come with the industrial sheet metal, which ranges anywhere from 22” round duct to 11’x3’ heavy industrial sheet metal.

In preparation for the project, Tweet/Garot put an enormous amount of preplanning in place to ensure a successful transition back to the owner.  Tweet/Garot takes tremendous pride in our work that enables Sappi to continue to deliver world class fiber.